0 XP

Lien action and its notice

365 days to start the lien action

Under O.C.G.A. 44-14-361.1(a)(3), the lien claimant must commence a lien action within 365 days from the date the claim of lien is filed for record.

  • "12 months from the date the claim became due" is the old rule and a common error.
  • 90 days is the time to file the claim of lien after completion, not the time to sue.
  • 365 days runs from the lien filing, not from completion of the work.

What counts as a lien action

O.C.G.A. 44-14-360(2.1) defines a lien action as:

  • a lawsuit,
  • a proof of claim in a bankruptcy case, or
  • a binding arbitration.

A notice of commencement is none of these. It is a project-start filing under 44-14-361.5, not a proceeding to enforce a lien.

The notice of commencement of lien action: 30 days

Once the lien action is commenced, the claimant must file a notice of commencement of lien action within 30 days after the lien action is commenced (44-14-361.1(a)(3)). It is filed with the clerk of superior court of the county where the lien was filed.

Worked example: suit filed May 10. May 10 + 21 days = May 31, plus 9 more = June 9.

  • May 24 uses the old 14-day figure, the common error.
  • May 20 uses 10 days, the copy-on-request period.
  • August 8 uses 90 days, the claim of lien period.

Required contents

The statute lists what the notice must contain:

  • a caption naming the then owner and referring to a recorded instrument in the chain of title;
  • the court or arbitration venue;
  • the style and number of the action, with all party names;
  • the date the action was filed;
  • the book and page where the lien is recorded.

The trap: a legal description of the property is not required. A secondary source listed it in error.

Knowledge check

4 questions on what you just read. Each answer shows the full explanation and its source.

Loading…