176 figures and rules across 30 topics, each with the trap the exam sets and a question to try it on. The Georgia exams are open book: this sheet cannot go into the test centre, but it tells you what to tab in the books you can bring.

Bring the listed references. PSI does not supply them. The reference lists are in PSI Bulletin 971 (Business & Law and residential) and PSI Bulletin 1458 (NASCLA General Contractor).

Licensing RequirementsBusiness & Law

License trigger & scopes

O.C.G.A. 43-41-2 · license needed when higher of work value or compensation exceeds $2,500 · Residential-Basic: 1- and 2-family, townhouses ≤ 3 stories · Light Commercial: steel buildings up to 50,000 sq ft, multifamily under 25,000 sq ft

Use the higher figure, never the lower or an average

Multifamily and pre-engineered steel belong to Light Commercial, not Basic

Try itbl licensing 1 · easybl licensing 2 · mediumbl licensing 3 · mediumbl licensing 4 · hard

Unlicensed contractor & incidental work

43-41-17(b): contract unenforceable by unlicensed contractor in law or equity · no lien or bond claim · owner keeps remedies · surety still bound · 43-41-17(g) incidental work ≤ greater of $10,000 or 25% of contract at time of contracting

Test date: effective date, then last signature date, then first delivery — never completion

Greater of, not lesser: $60,000 → $15,000; $30,000 → $10,000

Try itbl licensing 5 · easybl licensing 6 · mediumbl licensing 7 · hardbl licensing 9 · mediumbl licensing 10 · hard

Experience & exam rules

Basic: 2 yrs + 2 projects in prior 2 yrs · Light Commercial: 2 projects in prior 4 yrs · GC: 4 yrs with ≥ 2 as/for a GC and ≥ 1 in admin, estimating, supervision or PM · third attempt: wait 1 calendar year + new application (Rules 553-3, 553-4-.01)

Field years without a management year fail the GC path

Reciprocity (553-2-.13) still requires the Georgia Business and Law exam

Try itbl licensing 12 · easybl licensing 13 · mediumbl licensing 14 · hardbl licensing 27 · mediumbl licensing 28 · easy

Net worth, insurance, cap

GC net worth $150,000 · Limited Tier & residential net worth $25,000 · GL per occurrence: Basic $300,000, Light Commercial/GC $500,000 · Limited Tier ≤ $1,000,000 per contract incl. change orders · workers' comp at 3+ regular employees (O.C.G.A. 34-9-2)

Change orders cannot push past $1,000,000; it is per contract, not annual

2 employees: workers' comp not required

Try itbl licensing 15 · easybl licensing 16 · mediumbl licensing 17 · mediumbl licensing 18 · mediumbl licensing 19 · hard

Renewal & CE

Renew every 2 years by June 30 of even-numbered years · late July 1–December 31 with penalty · no renewal by December 31 = revocation · CE: Basic 3 hrs/yr, Light Commercial 6 hrs/yr, CE year July 1–June 30 (Rules 553-12-.01, .02, .05, .06)

Odd-numbered years is the trap

Penalty period cannot be used in the next cycle

Try itbl licensing 24 · easybl licensing 25 · mediumbl licensing 26 · medium

Estimating and BiddingBusiness & Law

Public-works retainage

O.C.G.A. 13-10-80 (contracts on/after July 1, 2022): retainage ≤ 5% of each progress payment · pay retainage within 30 days of invoice at substantial completion · hold ≤ 200% of each incomplete item · excludes DOT road work, projects under $150,000 or under 45 days

10% until 50% completion is the pre-2022 rule

$240,000 × 0.05 = $12,000; $7,500 punch list × 2.00 = $15,000

Try itbl estimating 12 · easybl estimating 13 · mediumbl estimating 14 · mediumbl estimating 15 · hardbl estimating 16 · hard

Business Organization and Financial ManagementBusiness & Law

Qualifying agent

Affidavit: final approval authority over all construction work and all business matters incl. contracts, performance and finances (Rule 553-3) · agent leaving: notify within 45 days · business changes: 45 days (O.C.G.A. 43-41-9) · June 10 + 45 = July 25

Construction-only authority fails if CFO decides contracts

90 days is the corporate registration period, not licensing notice

Try itbl business finance 16 · easybl business finance 17 · easybl business finance 18 · mediumbl business finance 19 · mediumbl business finance 21 · hard

SOS annual registration

Window January 1–April 1 each year (590-7-4-.03; O.C.G.A. 14-2-1622) · advance up to 3 calendar years · new domestic corp: within 90 days of articles (March 3 → June 1) · articles after October 1 or foreign qualification: January 1–April 1 next year (590-7-4-.02)

April 1 is the due date, January 1 the earliest

90-day rule does not apply after October 1 or to foreign corporations

Try itbl business finance 22 · easybl business finance 23 · easybl business finance 24 · mediumbl business finance 25 · mediumbl business finance 26 · hard

Tax LawsBusiness & Law

Deposit schedule

26 CFR 31.6302-1: lookback July 1–June 30 before prior year · ≤ $50,000 monthly (by 15th of next month) · over $50,000 semiweekly (Wed–Fri paydays → next Wednesday; Sat–Tue → next Friday) · $100,000 in one day → deposit next day, semiweekly rest of year and next year

Exactly $50,000 is monthly; calendar-year lookback is the trap

2026 lookback: July 1, 2024–June 30, 2025

Try itbl tax 14 · mediumbl tax 15 · mediumbl tax 16 · hardbl tax 17 · hardbl tax 19 · medium

Employee vs contractor

Pub 15-A: employee if business has the right to control what is done and how · categories: behavioral, financial (investment, profit or loss), type of relationship (contract, permanency)

The contract label does not decide

Right to control counts even if never exercised

Try itbl tax 25 · easybl tax 26 · mediumbl tax 27 · mediumbl tax 28 · hard

Labor LawsBusiness & Law

EEO coverage

Title VII & ADA: 15+ employees each working day in 20+ calendar weeks, current or preceding year (42 U.S.C. 2000e, 12111) · ADEA: 20 employees (EEOC Compliance Manual §2)

17 employees: Title VII and ADA yes, ADEA no

50 is from a different law

Try itbl labor 26 · easybl labor 27 · mediumbl labor 28 · hard

Project Management and Lien LawBusiness & Law

Lien waiver

44-14-366(g)(2): effective at earliest of funds received, separate written acknowledgment of payment in full, or 90 days after execution · affidavit of nonpayment filed in property county within 90 days · copy to owner within 7 days · ≥ 12-point font

Waiver becomes effective at day 90 even unpaid: January 10, 2025 → April 10, 2025

Delivery to owner is not a trigger

Try itbl lien pm 19 · mediumbl lien pm 20 · hardbl lien pm 21 · easybl lien pm 22 · medium

Unlicensed & warranty

43-41-17(b): contracts on/after July 1, 2008 unenforceable by unlicensed contractor, no lien or bond claim · surety still bound · 553-7-.01: written warranty when value or compensation exceeds $2,500.00 · NAHB Residential Construction Performance Guidelines

Exactly $2,500 does not trigger the warranty

553-9-.01(o) discipline needs reasonable reliance and actual financial loss

Try itbl lien pm 23 · mediumbl lien pm 24 · hardbl lien pm 25 · easybl lien pm 26 · mediumbl lien pm 27 · medium

ContractsBusiness & Law

Lien waiver & affidavit

44-14-366(g)(2): effective at earliest of funds received, separate acknowledgment of payment in full, or 90 days · affidavit of nonpayment in property county before day 90 · copy to owner within 7 days by registered/certified mail or statutory overnight · ≥ 12-point font

January 10, 2025 → April 10, 2025; 60 days is the old period

Not in privity with owner: also copy contractor at NOC address

Try itbl contracts 22 · mediumbl contracts 23 · hardbl contracts 24 · mediumbl contracts 26 · mediumbl contracts 27 · hard

Risk ManagementBusiness & Law

Insurance notice

553-4-.06(4): written notice of insurance change within 30 days · certificate maintained with division, condition of renewal · March 1 → March 31

Not at next renewal

Insurance is not needed only at application

Try itbl risk 11 · easybl risk 12 · mediumbl risk 13 · medium

OSHA reporting

29 CFR 1904.39: fatality 8 hrs (death within 30 days) · hospitalization, amputation, eye loss 24 hrs · clock starts when employer learns · small-employer exemption does not excuse reporting

Amputation 10 a.m., learned 2 p.m. → 2 p.m. next day

Death 45 days after incident: no fatality report

Try itbl risk 18 · mediumbl risk 19 · easybl risk 20 · hardbl risk 21 · hard

Workers' comp premium

Premium = (Payroll ÷ 100) × Rate × Mod · $70,000 ÷ 100 × 0.750 = $525 · mod above 1.00 = debit, below 1.00 = credit (NCCI)
Rate
classification rate per $100 of payroll
Mod
experience modification factor

Rate is per $100, not per $1,000

1.25 mod raises $100,000 to $125,000; 0.75 lowers to $75,000

Try itbl risk 25 · mediumbl risk 26 · hardbl risk 27 · mediumbl risk 28 · easy

Environmental and SafetyBusiness & Law

Excavation protection

1926.652: protective system at 5 ft or deeper unless stable rock · under 5 ft only if competent person finds no cave-in indication · 20 ft or deeper: registered PE design · manufacturer tabulated data only for support and shield systems · 1926.651(k): inspect daily and after rain

Under 5 ft is not automatically exempt

Weekly inspection is the trap

Try itbl env safety 16 · easybl env safety 17 · mediumbl env safety 18 · mediumbl env safety 19 · easybl env safety 22 · medium

Default slope

1926.652(b)(1): max 1.5H : 1V (34° from horizontal) · run = 1.5 × D · 8 ft deep → 12 ft
H
horizontal run
V
vertical rise
D
trench depth

Reversing to 1H : 1.5V gives 5.3 ft, far too steep

1 : 1 at 45° is steeper than allowed

Try itbl env safety 20 · mediumbl env safety 21 · hard

Sitework, Footings and Foundation (Residential)Residential

Egress, spoil, inspections

Egress in trench ≥ 4 ft deep · max 25 ft lateral travel to it · spoil and equipment ≥ 2 ft from edge or retained · competent-person inspection daily, as needed, after every rainstorm (29 CFR 1926.651(c)(2), (j)(2), (k)(1))

4 ft is the egress trigger; 5 ft is the protective-system trigger

25 ft is maximum worker travel, not a ladder spacing; 18 in. of setback fails the 2 ft rule

Try itres sitework 1 · easyres sitework 2 · mediumres sitework 3 · easyres sitework 4 · mediumres sitework 5 · medium

Cave-in protection trigger

Protective system required at ≥ 5 ft · exempt only in stable rock, or under 5 ft with no competent-person indication of cave-in · dig ≤ 2 ft below shield if shield rated for full depth and no soil loss (29 CFR 1926.652(a)(1), (g)(2))

Under 5 ft is not automatic: signs of cave-in still require protection

An 8 ft shield in a 10 ft trench fails even with a 2 ft gap

Try itres sitework 6 · easyres sitework 7 · mediumres sitework 8 · hardres sitework 9 · mediumres sitework 10 · hard

Soil classification

Type A ≥ 1.5 tsf (144 kPa), not fissured · Type B over 0.5 to under 1.5 tsf, fissured, angular gravel, silt · Type C ≤ 0.5 tsf (48 kPa), granular, submerged or seeping · layered = weakest layer · ≥ 1 visual + ≥ 1 manual test (Subpart P App. A)

Fissured 2.0 tsf clay is Type B, not A; exactly 0.5 tsf is Type C

Classification needs both a visual and a manual test, not an engineer's lab report

Try itres sitework 11 · easyres sitework 12 · mediumres sitework 13 · mediumres sitework 14 · hardres sitework 16 · medium

Maximum slopes (H:V)

Type A 3/4:1 (53°) · Type B 1:1 (45°) · Type C 1-1/2:1 (34°) · unclassified = 1-1/2:1 · short-term 1/2:1 only Type A ≤ 12 ft deep open ≤ 24 h · ≤ 20 ft deep, else registered PE (Subpart P App. B; 1926.652(b)(1))

Ratios are horizontal:vertical; 10 ÷ 1.5 is the reversed-ratio trap

At 14 ft or 24 ft the short-term slope and the table no longer apply

Try itres sitework 17 · easyres sitework 19 · mediumres sitework 20 · hardres sitework 22 · medium

Top width and cutbacks

Setback per side = ratio × depth · top width = bottom + 2 × setback · distress: flatten ≥ 1/2H:1V (Type A 3/4 + 1/2 = 1-1/4:1) · Type A vertical lower portion ≤ 3-1/2 ft, 1:1 above for over 8 to 12 ft · Type B/C shield ≥ 18 in. above vertical side (App. B)

Type C 10 ft deep, 4 ft bottom: 4 + 15 + 15 = 34 ft; sloping one side gives 19 ft

18 in. is the shield extension, 3-1/2 ft the Type A vertical portion

Try itres sitework 18 · hardres sitework 21 · hardres sitework 23 · mediumres sitework 24 · medium

Footings, fill, bearing

Spread footing ≥ 6 in. thick · projection 2 in. ≤ P ≤ T · fill ≤ 24 in. clean sand/gravel or 8 in. earth · joist bearing 3 in. on masonry/concrete, 1-1/2 in. on wood/metal · sill plate ≥ 2 in. nominal (IRC R403.1.1, R506.2.1; GA R502.6)

8 in. wall on 6 in. footing: 12 in. min, 20 in. max width; 3-1/2 in. is slab, not footing

Swapping the 24 in./8 in. fill limits; 1-1/2 in. bearing on concrete

Try itres sitework 25 · easyres sitework 26 · hardres sitework 27 · mediumres sitework 28 · easyres sitework 29 · medium

Concrete and Concrete Reinforcement (Residential)Residential

Footing, slab, fill

Spread footing ≥ 6 in · projection P ≥ 2 in and ≤ T · width = wall + 2P · slab-on-ground ≥ 3½ in · fill ≤ 24 in clean sand/gravel or 8 in earth except where approved (IRC R403.1.1, R506.1, R506.2.1)
P
projection each side
T
footing thickness

8 in wall on 8 in footing: max 24 in, min 12 in; capping P at 6 in gives 20 in

14 in of earth needs approval; 24 in is the sand/gravel limit

Try itres concrete 1 · easyres concrete 2 · mediumres concrete 3 · hardres concrete 4 · easyres concrete 6 · medium

Bearing and cover

GA R502.6: ≥ 3 in bearing on masonry/concrete, 1½ in on wood/metal, direct or on ≥ 2 in nominal sill · cover cast against earth 3 in (ACI 318-19 Table 20.5.1.3.1; ACI 318-14 Table 20.6.1.3.1) · lap splice 318-14 §25.5.2, development §25.4.2

1½ in is bearing on wood/metal, not concrete; 2 in is sill thickness

2018 IBC uses ACI 318-14 table numbers, not 318-19

Try itres concrete 7 · easyres concrete 8 · mediumres concrete 9 · easyres concrete 10 · mediumres concrete 11 · medium

Field test standards

C31 make and cure cylinders · C39 compression test · C143 slump · C172 sampling · C231 air, pressure method · C173 air, volumetric · C138 density and yield (ACI Contractor's Guide ch. 2)

C31 molds in the field; C39 is the lab break

C231 is pressure, C173 is volumetric

Try itres concrete 12 · easyres concrete 13 · medium

Formwork lateral pressure

Column p = Cw·Cc(150 + 9000R/T) ≤ 3000·Cw·Cc · wall p = Cw·Cc(150 + 43,400/T + 2800R/T), ≥ 600·Cw, ≤ 2000·Cw·Cc · never over wh · wall if any plan dimension over 6.5 ft · pumped from bottom: wh × 1.25 · Cw = 0.5(1 + w/145) ≥ 0.80 below 140 pcf (ACI Contractor's Guide ch. 5)
p
lateral pressure, psf
R
rate of placement, ft/hr
T
concrete temperature, °F
w
unit weight, pcf
h
form height, ft

2 ft × 2 ft column 10 ft: 1,650 psf capped at wh = 1,500 psf; wall 2,635 psf capped at 2,000

80 pcf gives 0.776, so Cw = 0.80; 3,000 psf is the column max only

Try itres concrete 14 · mediumres concrete 15 · hardres concrete 16 · hardres concrete 17 · hardres concrete 18 · hard

Loads, shoring, stripping

Construction loads only on a qualified structural person's information · guard all protruding rebar · inspect shoring immediately before, during, after placement · no raising single-post shores after placement · strip on plan/spec conditions or ASTM strength tests (29 CFR 1926.701(a)-(b), 1926.703(b)(3), (b)(9), (e)(1))

The rule sets no 7-day or 28-day stripping time and no 75% strength figure

One inspection before placement misses during and after

Try itres concrete 20 · easyres concrete 21 · easyres concrete 22 · mediumres concrete 23 · mediumres concrete 24 · medium

Metals (Residential-Light Commercial)Residential

Controlled decking zone

CDZ ≤ 90 ft wide × 90 ft deep from leading edge · unsecured decking ≤ 3,000 sq ft · no final deck attachments or shear connectors inside · access limited to trained leading-edge workers (29 CFR 1926.760(c))

8,100 sq ft is the zone area, not the unsecured-decking limit

4,000 lb is a decking bundle, 1,000 lb a bridging bundle

Try itres metals 6 · mediumres metals 7 · easyres metals 8 · mediumres metals 9 · medium

Bolting and anchor rods

≥ 2 bolts per connection wrench-tight before release · diagonal bracing ≥ 1 bolt · cantilever extra bolts: competent person · columns ≥ 4 anchor rods (posts under 300 lb excluded) · rod repair needs structural engineer of record + written notice from controlling contractor (29 CFR 1926.755, 1926.756(a)-(b))

Two bolts is general, one is diagonal bracing; four is anchor rods

A like-for-like rod replacement still needs EOR approval

Try itres metals 10 · easyres metals 11 · mediumres metals 12 · mediumres metals 13 · easyres metals 16 · medium

Column loads and height

Anchor rod assembly and splices resist 300 lb at 18 in from column face each direction at top of shaft · perimeter columns ≥ 48 in above finished floor · cable holes 42-45 in (29 CFR 1926.755(a)(2), 1926.756(d)-(e))

The 300 lb at 18 in load applies to both anchorage and splices

42 in is the cable-hole height, 48 in the column extension

Try itres metals 14 · mediumres metals 15 · hardres metals 17 · mediumres metals 18 · easy

Multi-story limits and covers

≤ 8 stories erection floor to top permanent floor · unfinished bolting/welding ≤ 4 floors or 48 ft, whichever is less · decked floor or nets within 2 stories or 30 ft, whichever is less · covers hold 2× load (29 CFR 1926.754(b), (e)(3))

14 ft stories: 4 × 14 = 56 ft, so 48 ft governs; 12 ft stories: 24 ft governs

112 ft wrongly applies the 8-story limit

Try itres metals 19 · easyres metals 20 · hardres metals 21 · hardres metals 22 · easy

Steel joists

Stabilizer plate ≥ 6 × 6 in, ≥ 3 in below bottom chord, 13/16 in hole · K-series ends: two 1/8 in welds 1 in long or two 1/2 in bolts · LH/DLH/girders: two 1/4 in welds 2 in long or two 3/4 in bolts · over 60 ft in tandem · 60-100 ft ≤ 2 workers · bridging bundle ≤ 1,000 lb on ≥ 3 joists within 1 ft of secured end (29 CFR 1926.757)

K-series and LH/girder values are the swap trap

18 in from secured end fails the 1 ft limit; 1,200 lb fails 1,000 lb

Try itres metals 23 · mediumres metals 24 · mediumres metals 25 · hardres metals 26 · mediumres metals 28 · hard

Masonry (Residential-Basic and Residential-Light Commercial)Residential

Mortar and cold weather

Modular 3/8 in joints: 5.5 cu ft per 100 sq ft or 8.1 cu ft per 1000 brick · 1/2 in joints: 6.9 per 100 sq ft, 10.3 per 1000 · mortar waste 15-25% · 8 bags per 1000 brick includes waste · cold weather below 40°F (4.4°C) (BIA TN 10; CMHA TEK 03-01C)

Mixing per-area and per-1000-brick rates; 5000 brick = 40 bags, no waste added

32°F is freezing, not the 40°F threshold

Try itres masonry 23 · mediumres masonry 24 · mediumres masonry 26 · mediumres masonry 27 · hardres masonry 28 · medium

Carpentry (Residential)Residential

Roofing (Residential)Residential

Georgia roofing amendments

GA DCA 2018 IRC amendments (rev. Jan 1, 2020): no Chapter 9 changes · R806.5 Item 5.2 deleted without substitution · Appendix U applies only where adopted by local ordinance

Assuming Georgia changed drip edge, valley or re-cover rules

AU408 is not a statewide mandate

Try itres roofing 1 · easyres roofing 2 · mediumres roofing 3 · medium

Roof fall protection

Trigger 6 ft · low slope ≤ 4:12, steep over 4:12 · monitor alone only ≤ 50 ft wide · steep: guardrail with toeboards, nets or PFAS · warning line 6 ft parallel / 10 ft perpendicular to equipment, 34-39 in high · guardrail 42 ± 3 in, 200 lb · PFAS 1,800 lb, 6 ft free fall, 3.5 ft decel, anchor 5,000 lb (29 CFR 1926.500-.502)

Exactly 4:12 is low slope; 60 ft wide roof bars monitor alone

34 in is warning-line height, not distance; 900 lb is the body-belt figure

Try itres roofing 20 · easyres roofing 22 · mediumres roofing 24 · hardres roofing 25 · mediumres roofing 26 · medium

General Code and Construction Knowledge (Residential)Residential

Garage separation

Residence and attics: ≥ 1/2 in gypsum garage side · habitable rooms above: ≥ 5/8 in Type X · supporting structure: ≥ 1/2 in · detached under 3 ft from dwelling: 1/2 in on interior of walls within that area (IRC Table R302.6)

1/2 in under a bedroom is the trap

Beam and posts cannot be left bare

Try itres code 1 · easyres code 2 · easyres code 3 · mediumres code 4 · medium

Snow load limit

Ground snow load over 70 psf (3.35 kPa): accepted engineering practice, not prescriptive Ch. 5, 6, 8 (IRC R301.2.3)

75 psf is out of the prescriptive tables

Upsizing rafters is still prescriptive

Try itres code 16 · easyres code 17 · medium

Georgia energy envelope

Air leakage under 5 ACH50, CZ 2-4, by certified DET verifier (E779, E1827, RESNET/ICC 380) · walls R-13 · ceiling R-38 · kneewall R-18 · U-0.35, SHGC 0.27 · skylight U-0.65 CZ2, U-0.55 CZ3-4 · basement 10/13 CZ4, 5/13 CZ3 · slab 0 (GA-amended 2015 IECC R402.4.1.2, Table R402.1.2)

Exactly 5.0 ACH50 fails; 3 ACH50 and R-20 are unamended IECC

ASTM E119 is not a listed test

Try itres code 18 · easyres code 19 · mediumres code 22 · mediumres code 23 · mediumres code 24 · easy

IBC height and area

Height: grade plane to average highest roof, no parapets · story above grade if floor above over 6 ft over grade plane · If = [F/P − 0.25] × W/30, W ≤ 30 ft · area increase only NFPA 13 · 13R: R max 4 stories, 60 ft (IBC 202, 506.3.3 Eq. 5-5, Tables 504.3/504.4, 506.2)
If
frontage increase factor
F
perimeter fronting open space, ft
P
building perimeter, ft
W
open space width, ft

45 ft open space still uses W/30 = 1

13R gets height increase only, not area

Try itres code 28 · easyres code 29 · mediumres code 30 · mediumres code 31 · hardres code 33 · hard

Associated Trades (Residential)Residential

Glazing near doors

Within 24 in of door edge and bottom under 60 in · includes perpendicular glazing on hinge side of in-swinging door · exempt: latch side perpendicular, closet ≤ 3 ft deep, intervening wall (IRC R308.4.2)

Hinge side is covered; latch side is exempt

36 in and 18 in are window and stair figures

Try itres trades 7 · easyres trades 8 · mediumres trades 9 · medium

Wet areas and stairs

Tub/shower/pool walls: bottom under 60 in, exempt if over 60 in horizontal from water's edge · stair bottom: under 36 in above landing within 60 in arc under 180° · guard exception: glass over 18 in from R312 guard (IRC R308.4.5, R308.4.7)

72 in from water's edge is exempt

36 in is the stair height trigger, not the arc

Try itres trades 13 · easyres trades 14 · mediumres trades 15 · hardres trades 16 · hard

Georgia insulation and ducts

Floor R-19 CZ 3-4 (R-13 CZ2) · cantilever R-30 with blocking (fn j) · R-30 meets R-38 if full height over top plate, 100% ceiling · R-19 under HVAC platform ≤ 32 sq ft + 32 in passage · duct leakage ≤ 6 cfm per 100 sq ft · attic ducts R-8 ≥ 3 in, R-6 under 3 in (GA-amended 2015 IECC Table R402.1.2, R402.2.1, R403.3.3; R403.3.1)

2,400 sq ft house: 24 × 6 = 144 cfm; 4 cfm is unamended IECC

Ducts inside the envelope are exempt; vented-attic ducts are not

Try itres trades 18 · easyres trades 19 · mediumres trades 21 · hardres trades 22 · easyres trades 23 · medium

OSHA Safety (Residential)Residential

Personal fall arrest

Harness arresting force ≤ 1,800 lb · free fall ≤ 6 ft · deceleration ≤ 3.5 ft · anchorage 5,000 lb per employee · body belts positioning only since Jan 1, 1998 (29 CFR 1926.502(d))

Two workers on one anchorage: 10,000 lb

Swapping 6 ft free fall and 3.5 ft deceleration; 900 lb is body belt

Try itres osha 6 · easyres osha 7 · mediumres osha 8 · hardres osha 9 · medium

Scaffolds

Fall protection over 10 ft · toprail 36-45 in before Jan 1, 2000, 38-45 in after · components 4× max intended load · suspension ropes 6× (29 CFR 1926.451)

9 ft scaffold needs none; 9 ft edge needs protection at the 6 ft trigger

750 lb plank: 3,000 lb

Try itres osha 10 · mediumres osha 11 · hardres osha 12 · medium

Ladders and stairs

Rungs 10-14 in o.c. · portable rails ≥ 11.5 in, fixed 16 in · Type 1A 3.3×, others 4× · job-made wood ladder foot at L/8 · stair or ladder at ≥ 19 in break · stairs 30°-50° · rails at 4 risers or over 30 in rise, whichever is less · stairrail ≥ 36 in (29 CFR 1926.1051-.1053)
L
working length of ladder

300 lb Type 1A: 990 lb; 16 ft job-made ladder: 2 ft

4 risers at 28 in still needs rails

Try itres osha 13 · easyres osha 14 · easyres osha 15 · hardres osha 16 · hardres osha 19 · medium

GFCI and AEGCP

GFCI or AEGCP, either one · 120 V, 1-phase, 15 and 20 A outlets not in permanent wiring · AEGCP tests every 3 months (6 months if not exposed) · exempt: 2-wire 1-phase generator ≤ 5 kW, conductors insulated from frame (29 CFR 1926.404(b)(1))

Requiring both GFCI and AEGCP

Daily is the visual check, not the test

Try itres osha 21 · easyres osha 22 · mediumres osha 23 · mediumres osha 24 · hard

Recordkeeping

Record on 300/301 within 7 calendar days · post 300A Feb 1-Apr 30 · keep 5 years after year end · ≤ 10 employees exempt from records, not reporting · report fatality 8 h, hospitalization/amputation/eye 24 h (29 CFR 1904.1, .29, .32, .33, .39)

2025 records kept to Dec 31, 2030, not 2028

Small employer still reports loss of an eye in 24 h

Try itres osha 25 · easyres osha 26 · mediumres osha 27 · hardres osha 28 · medium

General RequirementsGeneral Contractor

Pedestrian protection

IBC Table 3306.1 · ≤ 8 ft high and under 5 ft from lot line: construction railings · over 8 ft high: under 5 ft or 5 ft to ¼H: barrier + covered walkway · ¼H to ½H: barrier only · over ½H: none · walkway ≥ 4 ft wide, 150 psf (3306.2) · barrier ≥ 8 ft high, full site length (3306.5)
H
height of construction

Work out ¼H and ½H first: a 36 ft building gives 9 ft and 18 ft; a 60 ft building gives 15 ft and 30 ft.

Walkway load is 150 psf, not 100 psf; 42 in is the construction railing height, 8 ft the barrier height.

Try itgc general req 1 · easygc general req 2 · hardgc general req 3 · hardgc general req 4 · mediumgc general req 5 · easy

Fire safety during construction

IBC 2021 Ch. 33 · extinguisher ≥ ordinary hazard at each stairway on floors with combustibles and in every shed (3309.1) · roofing: one 3-A 40-B:C on the roof · stairway (3310.1) and standpipe (3311.1) once over 40 ft above lowest fire department vehicle access, kept within one floor of highest secured decking · fire watch in nonworking hours (3314.1): over 40 ft above lowest adjacent grade or over 50,000 sq ft per story

Stairway and standpipe measure from fire department vehicle access; the fire watch measures from lowest adjacent grade (44 ft vs 34 ft case).

Fire watch triggers are independent: a 30 ft building with 60,000 sq ft stories still needs one.

Try itgc general req 7 · easygc general req 9 · mediumgc general req 10 · hardgc general req 12 · mediumgc general req 13 · medium

Crane near power lines

29 CFR 1926.1408 · assess 20 ft at maximum working radius · options: deenergize and ground, 20 ft, or Table A · Table A: ≤ 50 kV 10 ft · over 50 to 200 kV 15 ft · over 200 to 350 kV 20 ft · over 350 to 500 kV 25 ft · over 750 to 1,000 kV 45 ft · over 1,000 kV set by utility or RPE · voltage from utility within 2 working days

Each band includes its upper value: exactly 200 kV is 15 ft, 230 kV is 20 ft.

A flat 10 ft for any voltage is not an option; 24 hours is the OSHA reporting deadline, not the voltage deadline.

Try itgc general req 20 · mediumgc general req 21 · mediumgc general req 22 · mediumgc general req 23 · hardgc general req 25 · easy

Assured grounding program

29 CFR 1926.404(b)(1)(iii) · cords and cord-and-plug equipment exposed to damage: visual inspection before each day's use · tests before first use, after repair, after a damaging incident, and every ≤ 3 months · fixed cords and receptacles not exposed to damage: no daily visual, test every ≤ 6 months

Weekly or monthly visual inspection is wrong; it is before each day's use.

3 months is the test interval, not the visual inspection interval.

Try itgc general req 26 · easygc general req 27 · mediumgc general req 28 · hard

Fall protection and scaffolds

29 CFR 1926.501 · edges 6 ft or more (b)(1) · holes more than 6 ft (b)(4)(i) · dangerous equipment: protect even under 6 ft (b)(8) · overhand bricklaying reach over 10 in (b)(9) · wall opening: outside ≥ 6 ft and inside sill under 39 in (b)(14) · safety monitor alone only on low-slope roofs ≤ 50 ft wide · scaffolds 1926.451: fall protection over 10 ft, access over 2 ft, platform gaps ≤ 1 in, restrain above 4:1 every 26 ft (20 ft if ≤ 3 ft wide)

Scaffold height-to-base 36 ÷ 5 = 7.2 to 1 needs ties; width only changes the 20 ft vs 26 ft spacing.

6 in is the scaffold platform end extension and 39 in the wall-opening sill, not the bricklaying reach.

Try itgc general req 29 · hardgc general req 30 · mediumgc general req 32 · mediumgc general req 33 · mediumgc general req 34 · hard

OSHA recordkeeping and reporting

29 CFR 1904 · exempt only if ≤ 10 employees at all times last year, counted at company-wide peak (1904.1) · report fatality within 8 hours only if death within 30 days of incident · in-patient hospitalization, amputation, eye loss: 24 hours (1904.39) · enter on 300 Log and 301 within 7 calendar days (1904.29(b)(3))

Peak headcount decides, not the average: 14 at the summer peak removes the exemption.

7 calendar days, not business days: Thursday, March 5 + 7 = Thursday, March 12.

Try itgc general req 39 · mediumgc general req 40 · mediumgc general req 41 · hard

Site ConstructionGeneral Contractor

Subpart P map

29 CFR 1926 Subpart P · 1926.650 scope and definitions (trench box = shield system) · 1926.651 specific requirements · 1926.652 protective systems · App. A soil classification · App. B sloping and benching · App. C timber shoring · App. D aluminum hydraulic shoring · App. E alternatives to timber shoring · App. F selection of protective systems

There is no 1926.653; the subpart ends at 1926.652 plus Appendices A to F.

The 20 ft registered-engineer limit for sloping is in Appendix B, not 1926.652.

Try itgc site 1 · easygc site 2 · easygc site 3 · easygc site 4 · medium

Soil classification

Appendix A · cohesive unconfined compressive strength: Type A ≥ 1.5 tsf · Type B over 0.5 to under 1.5 tsf · Type C ≤ 0.5 tsf · caliche and hardpan = Type A · fissured or vibrated soil drops to Type B · layers dipping into the cut at 4H:1V or steeper = Type C · unstable rock: dry Type B, submerged Type C

Exactly 1.5 tsf is Type A, not B.

2.0 tsf clay next to heavy traffic is Type B because of vibration; loamy sand is Type C.

Try itgc site 6 · easygc site 7 · mediumgc site 9 · mediumgc site 10 · mediumgc site 11 · hard

Maximum allowable slopes

Table B-1 (H:V) · Type A ¾:1 (53°) · Type B 1:1 (45°) · Type C 1½:1 (34°) · short-term Type A ½:1 (63°) only if ≤ 12 ft deep and open ≤ 24 h · unclassified soil 1½H:1V to Type C configurations (1926.652(b)(1)) · over 20 ft deep: registered PE design

Ratios are horizontal to vertical; 34° is measured from horizontal, not vertical (56°).

The ½:1 short-term slope never applies to Type B, beyond 12 ft, or past 24 hours.

Try itgc site 13 · easygc site 14 · mediumgc site 15 · mediumgc site 19 · easygc site 20 · easy

Sloped trench geometry

run = ratio × depth · top width = bottom + 2 × run · volume yd³ = (bottom + top) ÷ 2 × depth × length ÷ 27
ratio
Table B-1 horizontal run per 1 ft of depth

Type B, 8 ft deep, 3 ft bottom: 3 + 8 + 8 = 19 ft; Type C 12 ft deep runs 1.5 × 12 = 18 ft, not 12 ÷ 1.5 = 8 ft.

Use the average width and divide ft³ by 27, not 9: (2 + 11) ÷ 2 × 6 × 100 ÷ 27 = 144.4 yd³.

Try itgc site 16 · mediumgc site 17 · hardgc site 18 · medium

Egress and protective systems

1926.651(c)(2) egress in trenches 4 ft or more deep, ≤ 25 ft lateral travel · 1926.652(a)(1) protective system unless stable rock or under 5 ft with competent person finding no cave-in indication · spoil and equipment ≥ 2 ft from edge (1926.651(j)(2)) · dig ≤ 2 ft below a shield designed for full depth with no soil loss (1926.652(g)(2))

4 ft 8 in deep: egress yes, protective system no; the 4 ft and 5 ft triggers get swapped.

Each ladder covers 50 ft: 300 ÷ 50 = 6 ladders; 12 ft trench → shield bottom no higher than 10 ft.

Try itgc site 5 · mediumgc site 22 · hardgc site 23 · hardgc site 24 · medium

Proctor compaction

ASTM D698 Standard: 5.50 lbf rammer, 12.0 in. drop, 12,400 ft-lbf/ft³ (600 kN-m/m³) · ASTM D1557 Modified: 10.00 lbf rammer, 18.00 in. drop, 56,000 ft-lbf/ft³ (2,700 kN-m/m³) · 56,000 ÷ 12,400 ≈ 4.5 · curve gives maximum dry unit weight and optimum water content

Swapping rammer weight and drop between Standard and Modified is the set trap.

1.5 is only the drop ratio and 1.8 only the weight ratio; the effort ratio is about 4.5.

Try itgc site 25 · easygc site 26 · mediumgc site 27 · mediumgc site 28 · hard

ConcreteGeneral Contractor

Strength acceptance

ACI 318-19 · f'c based on 28-day tests (§19.2.1.3) · low-test limit (§26.12.3.1): f'c ≤ 5000 psi → no test below f'c − 500 psi · f'c over 5000 psi → no test below f'c − 0.10 f'c
f'c
specified compressive strength

4000 psi → 3500 psi floor; 6000 psi → 5400 psi; 8000 psi → 7200 psi, so 7300 psi passes.

7-day breaks only track strength gain; they are never the acceptance test.

Try itgc concrete 1 · easygc concrete 2 · mediumgc concrete 3 · mediumgc concrete 4 · hardgc concrete 5 · easy

Concrete volume and small-volume waiver

yd³ = L × W × D (ft) ÷ 27 · inches ÷ 12 first · IBC 2009 §1905.6.2: under 50 yd³ (38 m³) of a given class → strength tests not required if the building official approves evidence of satisfactory strength

Divide by 27, not 9 or 3: 100 × 2 × 1 = 200 ft³ = 7.41 yd³; 8 in = 0.667 ft, not 0.8 ft.

Count each class separately (30 and 35 yd³ both qualify), and the waiver still needs the official's approval.

Try itgc concrete 6 · easygc concrete 7 · easygc concrete 8 · hardgc concrete 9 · mediumgc concrete 10 · hard

Concrete cover

ACI 318 §20.5 (§20.6 in ACI 318-14) · cover = concrete surface to outermost surface of the steel, i.e. stirrups or ties where they enclose bars · IBC Table 1808.8.2 shallow foundations: no number, refers to ACI 318 §20.5

Measuring to main bars or a centerline overstates cover.

IBC Table 1808.8.2 prints no 3 in or 1½ in figure for shallow foundations.

Try itgc concrete 11 · easygc concrete 12 · mediumgc concrete 13 · mediumgc concrete 14 · hard

Cold weather definition

ACI 306R-16 §2.2: air temperature has fallen to, or is expected to fall below, 40°F (4°C) during the protection period · superseded ACI 306.1-90: average daily temperature = (high + low) ÷ 2 below 40°F for more than three successive days, ends when above 50°F for more than half of any 24 h

A 36°F forecast inside the protection period is cold weather even after a 58°F placement day.

The three-successive-days test is the old ACI 306.1-90 rule; (46 + 30) ÷ 2 = 38°F.

Try itgc concrete 15 · easygc concrete 16 · mediumgc concrete 17 · mediumgc concrete 18 · medium

Freeze protection

ACI 306R-16 §3.1(a): protect until 500 psi (3.5 MPa), about 48 hours at 50°F (10°C) · 500 psi covers only one freeze-thaw cycle · Table 7.2 days: no load not exposed 2 · no load exposed 3 (accelerated 2) · partial load exposed 6 (accelerated 4) · hours = days × 24

Partial load, exposed, accelerated = 4 × 24 = 96 hours; 144 hours uses the 6-day normal-set figure.

Table 7.2 periods are not form or shore removal times (§8.1).

Try itgc concrete 19 · easygc concrete 20 · mediumgc concrete 21 · hardgc concrete 22 · mediumgc concrete 23 · hard

OSHA concrete rules

29 CFR 1926.701 · (a) no construction loads until a person qualified in structural design confirms capacity · (b) guard protruding reinforcing steel to eliminate impalement · (c)(1) only employees essential to post-tensioning behind the jack · (c)(2) signs and barriers limit access during tensioning

No 7-day, 50 psf or 6 ft figure appears in the rule.

Caution tape or orange tape does not meet the barrier or impalement rules.

Try itgc concrete 25 · easygc concrete 26 · mediumgc concrete 27 · mediumgc concrete 28 · easy

MasonryGeneral Contractor

Mortar properties

ASTM C270-19a Table 1 minimum 28-day strength: M 2500 · S 1800 · N 750 · O 350 psi · water retention 75% all types · air max cement-lime M/S 12%, N/O 14% · mortar or masonry cement M/S 18%, N/O 20% · adhered veneer: Type N or S (IBC 2021 §2103.2.4)

Table 1 applies to laboratory-prepared mortar only; field-sampled cubes at 1400 psi cannot be judged against 1800 psi.

Order is M, S, N, O from strongest to weakest.

Try itgc masonry 2 · mediumgc masonry 6 · easygc masonry 7 · easygc masonry 9 · mediumgc masonry 10 · hard

Mortar proportions

ASTM C270-19a Table 2 lime per 1 part cement: M 1/4 · S over 1/4 to 1/2 · N over 1/2 to 1 1/4 · O over 1 1/4 to 2 1/2 · sand = 2 1/4 to 3 × (cement + lime) · unspecified: proportion requirements govern, except ASTM C1714 preblended → property (BIA TN 8)

1 : 1/2 Type S → 1 1/2 parts → 3 3/8 to 4 1/2 parts sand; 1 : 1 Type N → 6 parts max.

The upper multiplier is 3, not 3 1/2, and it applies to cement plus lime.

Try itgc masonry 11 · easygc masonry 12 · hardgc masonry 13 · mediumgc masonry 14 · mediumgc masonry 15 · hard

Movement joints

BIA TN 18A (2019) · brick expansion joints ≤ 20 ft o.c. with multiple openings, 25 ft without · ≥ 1/4 in. open space below shelf angles · movement = length × 0.0009 · Se = (wj × ej) ÷ 0.09 · brick expands (expansion joints), CMU shrinks (control joints per NCMA TEK 10-2C or 10-3)
Se
maximum expansion joint spacing, in.
wj
joint width, in.
ej
sealant compressibility, percent

Enter ej as a percent: (0.375 × 50) ÷ 0.09 = 208.3 in.; 0.50 gives an answer 100 times too small.

100 ft × 12 = 1200 in. × 0.0009 = 1.08 in.; control joints go in CMU, expansion joints in brick.

Try itgc masonry 20 · easygc masonry 21 · mediumgc masonry 22 · hardgc masonry 23 · mediumgc masonry 24 · easy

Veneer anchors and wall bracing

NCMA/CMHA TEK 3-6C high wind (qz 40 to 55 psf, mean roof height ≤ 60 ft): anchors ≤ 18 in. each way · openings over 16 in.: anchors within 12 in. of opening at ≤ 24 in. o.c. · 29 CFR 1926.706: limited access zone = wall height + 4 ft, full wall length, unscaffolded side · walls over 8 ft braced until permanent supports

The 12 in. and 24 in. opening figures get swapped.

14 ft 6 in wall → 18 ft 6 in zone on the side without scaffold.

Try itgc masonry 26 · mediumgc masonry 27 · mediumgc masonry 28 · hard

Masonry code references

IBC 2021 · grout: TMS 602 Article 2.2 (§2103.3) · construction including cold weather: TMS 602 or TMS 604 (§2104.1) · special inspection: Chapter 17 (§2101.3) · quality assurance: Chapter 17 and TMS 602 (§2105.1)

§2104.3 cold-weather rules were IBC 2009 and are gone.

ASTM C270 is the mortar standard, not the grout or inspection reference.

Try itgc masonry 1 · easygc masonry 3 · mediumgc masonry 4 · easygc masonry 5 · medium

MetalsGeneral Contractor

Steel erection fall protection

29 CFR 1926.760 · erectors over 15 ft: guardrail, safety net, personal fall arrest, positioning device or fall restraint · connectors: over two stories or 30 ft, whichever is less · controlled decking zone: over 15 ft up to 30 ft, ≤ 90 ft wide and 90 ft deep, ≤ 3,000 sq ft unsecured deck

A warning line is not one of the five systems.

13 ft stories → 2 × 13 = 26 ft governs; 3,400 − 3,000 = 400 sq ft of deck must be secured.

Try itgc metals 1 · easygc metals 2 · easygc metals 3 · mediumgc metals 4 · mediumgc metals 6 · hard

Footing strength notice

29 CFR 1926.752(a) · controlling contractor gives written notice · concrete ≥ 75 percent of intended minimum compressive design strength, by ASTM test of field-cured samples, or enough for erection loads

0.75 × 4,000 psi = 3,000 psi; 50 percent and full 28-day strength are wrong.

Verbal confirmation, laboratory-cured cylinders or elapsed days do not satisfy the rule.

Try itgc metals 7 · easygc metals 8 · mediumgc metals 9 · mediumgc metals 10 · medium

Anchor rods and connections

1926.755(a) ≥ 4 anchor rods, resist 300 lb eccentric load 18 in from column's extreme outer face · 1926.756(a)(1) ≥ 2 bolts per connection, same size and strength as erection drawings, wrench-tight before release · solid-web diagonal brace: 1 bolt per connection

12 in column: 12 ÷ 2 + 18 = 24 in from centerline.

Beam with 2 connections + brace with 2 connections = 4 + 2 = 6 bolts; count per connection, not per member.

Try itgc metals 11 · easygc metals 12 · hardgc metals 13 · easygc metals 14 · mediumgc metals 15 · hard

Multi-story limits

1926.754(b) · ≤ eight stories between erection floor and uppermost permanent floor · unfinished bolting or welding ≤ four floors or 48 ft, whichever is less · planked floor or nets within two stories or 30 ft, whichever is less

10 ft stories → 4 × 10 = 40 ft, not 48 ft.

18 ft stories → 2 × 18 = 36 ft, so 30 ft governs.

Try itgc metals 16 · easygc metals 17 · mediumgc metals 18 · medium

Joist erection and bridging

1926.757 · joist at column ≤ 60 ft: one employee releases without erection bridging · over 60 ft: set in tandem with all bridging unless qualified-person alternative in the erection plan · over 60 to 100 ft: two rows bolted diagonal bridging near third points · over 100 to 144 ft: all bolted diagonal, cables held until all installed and anchored · over 144 ft: erect per 1926.756

Two rows go near the third points, not nearest midspan.

A competent person's approval is not the alternative to tandem setting.

Try itgc metals 19 · mediumgc metals 20 · mediumgc metals 23 · hardgc metals 24 · mediumgc metals 25 · medium

Joist ends and landing loads

1926.757(b) ends: K-series two 1/8 in fillet welds 1 in long or two 1/2 in bolts · LH, DLH, joist girders two 1/4 in welds 2 in long or two 3/4 in bolts · (e) decking bundle ≤ 4,000 lb on ≥ 3 joists attached both ends with ≥ 1 row bridging · bridging bundle ≤ 1,000 lb on ≥ 3 joists secured one end, within 1 ft of secured end · no other construction loads until all bridging installed

1,400 lb of bridging → 2 bundles; a 3,600 lb deck bundle still needs one row of bridging first.

Insulation pallets get no bundle exception.

Try itgc metals 21 · easygc metals 22 · mediumgc metals 26 · hardgc metals 27 · mediumgc metals 28 · medium

WoodGeneral Contractor

Fire-retardant-treated wood

IBC 2303.2 · pressure-impregnated in closed vessels at ≥ 50 psig or treated during manufacture · ASTM E84 or UL 723 flame spread index ≤ 25, test extended 20 minutes, flame front ≤ 10.5 ft past burner · ASTM E2768 alternative (2024 §2303.2.1) · dried to ≤ 19% lumber, ≤ 15% wood structural panels (§2303.2.9)

A surface coating alone never makes FRTW, even at a flame spread index of 25 or less.

Lumber 19%, panels 15%; reversing them is the trap.

Try itgc wood 1 · easygc wood 2 · mediumgc wood 3 · mediumgc wood 4 · mediumgc wood 5 · hard

Decay protection

IBC 2304.12.1.2 · framing including sheathing on exterior foundation walls under 8 in (203 mm) from exposed earth: naturally durable or preservative-treated · preservative-treated wood conforms to AWPA U1 and M4 (2303.1.9)

Sheathing is covered: sill at 7 in and sheathing at 5 in both need treatment.

Naturally durable wood is an equal option to pressure-treated.

Try itgc wood 6 · easygc wood 7 · mediumgc wood 8 · mediumgc wood 9 · easy

Fasteners in treated wood

IBC 2021 2304.10.6.1 · hot-dipped zinc-coated galvanized (ASTM A153), stainless steel, silicon bronze or copper · staples: stainless only · ASTM B695 Class 55 mechanical zinc except nails, staples, timber rivets, wood screws, lag screws · plain carbon steel only in SBX/DOT or zinc borate wood, interior dry

Electro-galvanized steel is not permitted.

A bolt with nut and washer may use B695 Class 55; nails and lag screws may not.

Try itgc wood 10 · mediumgc wood 11 · mediumgc wood 12 · easygc wood 13 · hardgc wood 14 · medium

Type IV minimum sizes

IBC Table 2304.11 (sawn nominal; glulam and SCL net) · columns with floor loads: sawn 8 × 8, glulam 6¾ × 8¼, SCL 7 × 7½ · roof-only columns: sawn 6 × 8, glulam 5 × 8¼, SCL 5¼ × 7½ · floor beams and girders: sawn 6 × 10, glulam 5 × 10½, SCL 5¼ × 9½

A column carrying floor plus roof loads needs 8 × 8; 6 × 8 is roof-only.

Reading glulam sizes as nominal sawn sizes is the set error.

Try itgc wood 15 · easygc wood 16 · mediumgc wood 17 · mediumgc wood 18 · hardgc wood 19 · medium

Fireblocking

IBC 718.2.2 concealed walls: fireblock at ceiling and floor levels and horizontally ≤ 10 ft · 718.2.1 materials: 2 in nominal lumber, two 1 in nominal with broken lap joints, 0.719 in (23/32 in) wood structural panel with backed joints, 1/2 in gypsum board · draftstopping (718.3.1) allows 3/8 in panels and 1 in lumber

3/8 in panel is draftstopping only; fireblocking panels are 23/32 in with backed joints.

A single 1 in nominal board is draftstopping, not fireblocking.

Try itgc wood 20 · easygc wood 21 · mediumgc wood 22 · mediumgc wood 28 · medium

Draftstopping areas

IBC 2021 718.3 and 718.4, other than Group R · floor/ceiling areas ≤ 1,000 sq ft · attics ≤ 3,000 sq ft · areas = floor area ÷ limit, round up · R-2 ≤ 4 stories and ≤ 60 ft: attic ≤ 3,000 sq ft or every two dwelling units, whichever is smaller · waived with NFPA 13 sprinklers throughout (903.3.1.1)

7,500 ÷ 1,000 = 7.5 → 8 areas; 10,000 ÷ 3,000 = 3.33 → 4; never round down.

NFPA 13R alone does not waive draftstopping; 2 × 900 = 1,800 sq ft beats 3,000 sq ft.

Try itgc wood 23 · easygc wood 24 · hardgc wood 25 · mediumgc wood 26 · hardgc wood 27 · medium

Thermal and Moisture ProtectionGeneral Contractor

Minimum roof slopes

IBC 2021 §1507 · asphalt shingles 2:12 (17%), two underlayment layers from 2:12 to under 4:12 · clay and concrete tile 2½:12 (21%), two layers to 4:12 · standing-seam metal ¼:12 · lapped nonsoldered metal 3:12 (25%), ½:12 with lap sealant

4:12 is where double underlayment ends, not the shingle minimum; 3½:12 still needs two layers.

Tile on a 2:12 roof is not allowed; extra underlayment does not fix slope.

Try itgc thermal 1 · easygc thermal 2 · easygc thermal 3 · mediumgc thermal 5 · mediumgc thermal 7 · medium

Low-slope membranes

Built-up (§1507.10.1), modified bitumen, single-ply (§1507.12.1), sprayed foam: ¼:12 (2%) · coal-tar built-up only: ⅛:12 (1%) · drop = run (ft) × ¼ in

40 ft × ¼ in = 10 in; 5 in uses the coal-tar rate.

The ⅛:12 exception is for coal-tar built-up only.

Try itgc thermal 9 · easygc thermal 10 · mediumgc thermal 11 · hard

Secondary drainage

IBC 2021 §1502.2 · where roof drains are required and perimeter construction would trap water if primary drains allow buildup for any reason: secondary drains or scuppers, sized per §1611 and the IPC · scupper opening ≥ 4 inches (§1502.3)

Correctly sized primary drains do not remove the need for secondary drainage behind parapets.

12 in is the foundation waterproofing figure, not a scupper size.

Try itgc thermal 12 · mediumgc thermal 13 · easygc thermal 14 · medium

Vapor retarder classes

IBC 2021 Table 1404.3(1), ASTM E96 Procedure A (desiccant) · Class I ≤ 0.1 perm (sheet polyethylene, nonperforated aluminum foil) · Class II over 0.1 to ≤ 1.0 perm (kraft-faced batts, vapor retarder paint) · Class III over 1.0 to ≤ 10 perms (latex or enamel paint)

Exactly 1.0 perm is Class II; kraft facing is Class II, not Class I.

Procedure B (water method) is not the named test.

Try itgc thermal 15 · easygc thermal 16 · mediumgc thermal 17 · easygc thermal 18 · mediumgc thermal 19 · hard

Dampproofing and waterproofing

IBC 2021 §1805 · no hydrostatic pressure: dampproof top of footing to above grade, parge unit masonry first, e.g. ⅛ in ASTM C887 surface-bonding mortar or 3 lb per sq yd acrylic modified cement · hydrostatic pressure (per §1803.5.4): waterproof from bottom of wall to ≥ 12 in above maximum ground-water table, dampproof the rest

Stopping at the water table misses the 12 in: 3 ft 6 in + 1 ft = 4 ft 6 in waterproofed, 9 ft − 4 ft 6 in = 4 ft 6 in dampproofed.

Wall height and climate zone are not the trigger; hydrostatic pressure is.

Try itgc thermal 24 · mediumgc thermal 25 · mediumgc thermal 26 · hardgc thermal 27 · mediumgc thermal 29 · easy

Doors, Windows, and GlazingGeneral Contractor

Glazing in and near doors

IBC 2406.4.1 all door glazing is hazardous except openings a 3-in. sphere cannot pass, decorative, curved revolving-door panels, refrigerated cabinet doors · 2406.4.2 adjacent glazing: within 24-in. arc of either door edge (door closed) and bottom under 60 in. · exceptions: intervening wall or barrier; latch-side perpendicular only in one- and two-family dwellings or inside R-2 units

Measure the arc with the door closed, not open 90 degrees.

A Group B office sidelite 20 in. away with a 30 in. bottom edge needs safety glazing.

Try itgc openings 1 · mediumgc openings 2 · easygc openings 3 · hardgc openings 4 · medium

Windows and wet areas

IBC 2406.4.3 all four: pane over 9 sq ft · bottom under 18 in. · top over 36 in. · walking surface within 36 in. · exceptions: rail 34 to 38 in. at 50 plf, outboard insulating-glass pane ≥ 25 ft above grade · 2406.4.5 wet areas: bottom under 60 in., excepted over 60 in. horizontally from water's edge

2.5 × 3.5 = 8.75 sq ft fails the size test, so it is not hazardous; the four tests are not alternatives.

Only the outboard pane is exempt, and the height is 25 ft, not 12 ft.

Try itgc openings 5 · hardgc openings 6 · hardgc openings 7 · medium

Safety glazing categories

16 CFR 1201 · Category I 150 ft-lb · Category II 400 ft-lb · IBC Table 2406.2(1): 9 sq ft or less Category I for 2406.4.2 panels; over 9 sq ft Category II · sliding glass doors and wet-area enclosures always Category II · wired glass unlikely to pass Category II, fire doors only

A 7 sq ft patio sliding door lite is still Category II.

3 × 3.5 = 10.5 sq ft door lite is Category II.

Try itgc openings 8 · easygc openings 9 · mediumgc openings 10 · mediumgc openings 11 · hardgc openings 12 · medium

Fire-rated glazing

Fire-protection-rated: OH — XXX (IBC 716.1.2.2.2), NFPA 257 or UL 9 fire and hose stream, XXX = minutes, fire window openings · fire-resistance-rated: ASTM E119 or UL 263 (§703.4), agency label per Table 716.1(1), permanently on the glazing

OH — 45 means 45 minutes, not 4.5 hours or area.

OH glass is fire-protection-rated, not fire-resistance-rated; a removable frame label fails §703.4.

Try itgc openings 13 · mediumgc openings 14 · easygc openings 15 · mediumgc openings 16 · mediumgc openings 17 · hard

Egress door dimensions

IBC 1010.1.1 · clear width ≥ 32 in. from door face to stop, door open 90 degrees · leaf ≤ 48 in. nominal · 80 in. clear height, closers and stops ≥ 78 in. (1010.1.1.1) · no projection below 34 in.; ≤ 4 in. from 34 to 80 in. · exceptions: Type B units 31-3/4 in., single-user toilet 20 in.

A 36 in. leaf or 38 in. rough opening is not the clear width; 31-1/2 in. fails.

48 in. is the maximum leaf, not a minimum.

Try itgc openings 18 · easygc openings 19 · mediumgc openings 20 · easygc openings 21 · mediumgc openings 22 · hard

FinishesGeneral Contractor

Required finish by location

IBC Table 803.13 Groups B, E, M, R-1 (exit stairways / corridors / rooms): nonsprinklered A / B / C · sprinklered B / C / C · Group I-3 exit stairways stay Class A when sprinklered · sprinklered column only for NFPA 13 or 13R throughout

A partial sprinkler system uses the nonsprinklered column: Group B exits need Class A.

There is no blanket one-class reduction for I-3 exits.

Try itgc finishes 6 · mediumgc finishes 7 · mediumgc finishes 8 · hardgc finishes 9 · hard

Gypsum board standards

IBC Table 2508.1: gypsum panel products GA-216 or ASTM C840 · gypsum sheathing ASTM C1280 or GA-253 · veneer base ASTM C844 · no wallboard where directly exposed to water or continuous high humidity (2508.2) · rated joints treated; single-layer exception only over wood framing (2508.5)

Single-layer joints over steel framing still need treatment.

GA-216/C840 is for wallboard, C1280/GA-253 for sheathing.

Try itgc finishes 14 · easygc finishes 15 · mediumgc finishes 16 · easygc finishes 17 · medium

Gypsum fastener spacing

GA-216-2010 single layer · nails: ceilings 7 in. o.c., walls 8 in. o.c. · screws: ceilings 12 in., walls 16 in. with 16 in. framing, 12 in. with 24 in. framing · fasteners = spaces (length ÷ spacing, round up) + 1

96 ÷ 16 = 6 spaces → 7 screws; 144 ÷ 7 = 20.57 → 21 spaces → 22 nails.

16 in. wall screw spacing does not apply at 24 in. framing.

Try itgc finishes 18 · easygc finishes 19 · mediumgc finishes 20 · mediumgc finishes 21 · hard

Gypsum finish levels

GA-214-2021 · Level 0 none · Level 1 tape only (plenums, concealed areas) · Level 2 tape wiped plus one coat on fasteners (tile substrate, garages) · Level 3 heavy or medium texture · Level 4 two coats flat joints, one interior angles, three fasteners (flat paint) · Level 5 Level 4 plus skim coat (gloss, dark paint, critical lighting)

Gloss or deep-tone paint under critical lighting needs Level 5.

Tile backing is Level 2, not Level 4 or 5.

Try itgc finishes 22 · easygc finishes 23 · mediumgc finishes 24 · mediumgc finishes 25 · medium

Mechanical and Plumbing SystemsGeneral Contractor

Toilet facility location

IBC 2902.3 · path of travel ≤ 500 feet · not more than one story above or below the space served

Toilets on floor 1 cannot serve floor 3.

The limit is 500 feet, not 200 or 300 feet.

Try itgc mech plumb 6 · easygc mech plumb 7 · medium

Sprinkler triggers

IBC 2021 §903.2 · A-1: over 12,000 sq ft or ≥ 300 occupants · A-2: over 5,000 sq ft or ≥ 100 occupants, stories down to exit discharge · M and S-1: over 12,000 sq ft one fire area or over 24,000 sq ft combined all floors · Group R: always

Exactly 100 occupants triggers A-2; exactly 5,000 sq ft does not.

3 × 9,000 = 27,000 sq ft > 24,000 sq ft, even with each area under 12,000.

Try itgc mech plumb 8 · easygc mech plumb 9 · mediumgc mech plumb 11 · mediumgc mech plumb 12 · hardgc mech plumb 14 · easy

Drain slope and cleanouts

IPC 2021 Table 704.1 · ≤ 2½ in pipe 1/4 inch per foot · 3 to 6 in 1/8 inch per foot · ≥ 8 in 1/16 inch per foot · fall = length × slope · cleanout clearance: ≤ 6 in pipe 18 inches, ≥ 8 in pipe 36 inches

2½ in pipe is in the 1/4 group: 40 × 1/4 = 10 inches; 3 in pipe: 60 × 1/8 = 7.5 inches.

Using 1/8 for 2 in branches is the set error.

Try itgc mech plumb 16 · easygc mech plumb 17 · easygc mech plumb 18 · mediumgc mech plumb 19 · mediumgc mech plumb 21 · easy

Water pressure and T&P discharge

IPC 2021 §604.8 · static over 80 psi → pressure-reducing valve (ASSE 1003 or CSA B356, with strainer) reducing to ≤ 80 psi static · §608.1 prevent cross-connection contamination, device per Table 608.1 · IRC P2804.6.1 T&P discharge ≤ 6 inches above floor and ≥ 2 × pipe diameter

¾ in discharge pipe → at least 1½ inches above the floor.

An RPZ backflow preventer is not a pressure-reducing valve.

Try itgc mech plumb 23 · easygc mech plumb 24 · mediumgc mech plumb 25 · mediumgc mech plumb 27 · hard

Electrical SystemsGeneral Contractor

GFCI on temporary power

29 CFR 1926.404(b)(1)(ii) · 120-volt, single-phase, 15- and 20-ampere receptacles not part of permanent wiring · generator exemption: two-wire, single-phase, ≤ 5 kW, conductors insulated from frame · adds to all other grounding requirements

A 5 kW generator with bonded conductors is not exempt.

240-volt, 30-ampere or three-phase receptacles fall outside the rule.

Try itgc electrical 1 · easygc electrical 2 · hardgc electrical 3 · medium

Assured grounding program

1926.404(b)(1)(iii) · written program at jobsite · one or more competent persons · tests: grounding conductor continuity and correct attachment, not polarity · before first use and every ≤ 3 months (6 months fixed, not exposed) · record by logs or color coding, on the jobsite

Tested January 15 → next test by April 15, not July 15.

A brand-new cord must be tested before first use.

Try itgc electrical 4 · easygc electrical 5 · mediumgc electrical 6 · mediumgc electrical 7 · mediumgc electrical 9 · medium

Temporary wiring

1926.405(a)(2) · remove immediately on completion · feeders from a distribution center, open conductors on insulators ≤ 10 ft apart · branch conductors fastened ≤ 10 ft, never on the floor · lamps guarded, metal-case sockets grounded, not hung by cords unless designed for it · wet or conductive: ≤ 12 volts or 120-volt with GFCI

90 days is the general-industry holiday-lighting limit, not a construction rule.

24 volts is not the wet-location figure; 12 volts is.

Try itgc electrical 10 · easygc electrical 12 · easygc electrical 13 · mediumgc electrical 14 · mediumgc electrical 16 · hard

Deenergizing and tagging

29 CFR 1926.417 · tag at all points where the circuit can be energized · tag controls to be deactivated · tags plainly identify equipment or circuits · lock not required (OSHA 2006-09-28 interpretation); render inoperative, e.g. remove a fuse for each phase conductor

Tag both the local disconnect and the transfer switch.

Mandatory locks come from 1910.147 and 1910.333, not construction.

Try itgc electrical 21 · mediumgc electrical 22 · hardgc electrical 23 · easy

Power line clearances

Cranes, 1926.1408 Table A: ≤ 50 kV 10 ft · over 50 to 200 kV 15 ft · over 200 to 350 kV 20 ft · Subpart O, 1926.600(a)(6): 10 ft + 0.4 in per kV over 50 kV · in transit, boom lowered: under 50 kV 4 ft, over 50 to 345 kV 10 ft, to 750 kV 16 ft · not applicable if deenergized and visibly grounded or insulating barriers erected

115 kV backhoe: 65 × 0.4 = 26 in → 12 ft 2 in; apply 0.4 in only above 50 kV.

Exactly 50 kV is 10 ft; each range includes its upper bound.

Try itgc electrical 24 · easygc electrical 25 · mediumgc electrical 26 · hardgc electrical 27 · mediumgc electrical 28 · medium

Procurement and Contracting RequirementsGeneral Contractor

AIA agreements and GMP

A101-2017 stipulated sum, adopts A201-2017 · A102-2017 cost plus fee with GMP · §5.2.1 cost over GMP paid by Contractor without reimbursement · §12.1.5.2 schedule of values lines are not separate GMPs · liquidated damages (A101 §4.5) and retainage (A102 §12.1.8.1) are blanks

GMP 2,400,000 dollars, cost 2,515,000 dollars → Owner pays 2,400,000, Contractor absorbs 115,000.

A '10% until 50%, then 5%' figure is a party insertion, not AIA text.

Try itgc procurement 1 · easygc procurement 5 · easygc procurement 6 · mediumgc procurement 7 · hardgc procurement 8 · medium

Final payment and retainage

A101 §5.2.2 final payment ≤ 30 days after final Certificate · retainage §5.1.7.1 blank, limited by law; apply at Substantial Completion (§5.1.7.3) · O.C.G.A. 13-10-80 public work ≤ 5% of each progress payment · 13-11-6 pass retainage to subs within ten days · 13-11-4 default 15 days; contract terms control (13-11-7)

October 1 + 30 = October 31; April 8 + 10 = April 18.

10% until 50% completion is the pre-2022 Georgia public rule.

Try itgc procurement 13 · mediumgc procurement 14 · mediumgc procurement 16 · mediumgc procurement 17 · mediumgc procurement 18 · hard

A201 day counts

A201-2017 · §9.4.1 Architect acts within 7 days · §9.7 stop Work on seven additional days' notice · §2.5 Owner may correct after ten days · §3.7.4 concealed conditions: before disturbed, ≤ 14 days (A201-2007: 21) · §15.1.3.1 Claim within 21 days of later of event or recognition · §15.1.2 ≤ 10 years after Substantial Completion

Received May 1 → act by May 8; notice May 9 → stop May 16.

Claim runs from the later date: April 20 + 21 = May 11; rock seen March 3 → notice by March 17.

Try itgc procurement 9 · easygc procurement 11 · hardgc procurement 25 · mediumgc procurement 27 · easygc procurement 28 · hard

Changes in the Work

A201-2017 · Change Order: Owner, Contractor and Architect sign (§7.2.1) · Construction Change Directive: Owner and Architect (§7.3.1), used without total agreement (§7.3.2) · Contractor proceeds promptly (§7.3.6) · signed CCD becomes a Change Order (§7.3.7) · Addenda before execution, Modifications after (A101 Article 1)

The Contractor does not sign a CCD to make it effective.

Disagreeing with the price is no reason to stop CCD work.

Try itgc procurement 3 · mediumgc procurement 19 · easygc procurement 20 · easygc procurement 22 · mediumgc procurement 23 · medium

Closeout and termination

§9.8.1 Substantial Completion = usable for intended use · Contractor prepares punch list (§9.8.2) · correction period one year from Substantial Completion (§12.2.2.1) · special warranties in Owner's name, start at Substantial Completion (§3.5.2) · Contractor terminates after 30 consecutive days stopped (§14.1.1) or 60 days for repeated Owner failures (§14.1.4), on seven days' notice

The correction period is not a warranty limit or statute of limitations.

60 days applies only to repeated Owner failures; 90 days is a Miller Act period.

Try itgc procurement 31 · easygc procurement 33 · easygc procurement 36 · mediumgc procurement 37 · easygc procurement 40 · hard

Federal bonds and Miller Act

FAR 28.102-1 · performance and payment bonds over 150,000 dollars (statute still reads 100,000) · over 35,000 to 150,000: contracting officer selects two or more protections · performance bond 100% of original price + 100% of increases; payment bond no less · 40 U.S.C. 3133: second-tier notice to prime within 90 days of own last furnishing · suit within one year of own last labor, U.S. District Court, nothing below second tier

2,000,000 + 300,000 = 2,300,000 dollars; 50% payment bonds are wrong.

Last delivery March 10, 2026 → notice June 8, 2026, suit March 10, 2027; not from final acceptance.

Try itgc procurement 41 · easygc procurement 44 · mediumgc procurement 45 · mediumgc procurement 48 · hardgc procurement 50 · medium

Sources are the ones cited on each linked question. Standards figures: FGCS 1984, ASPRS 2014, NSSDA, NMAS 1947, ALTA/NSPS 2021, Georgia Board Rule 180-7.